PCW cooling water system installation and commissioning
The PCW cooling water system has entered installation and commissioning, with the plate heat exchanger, circulation pumps, control panel and temperature/pressure instruments wired and interlock-tested.
ZHUOCHUANG / INSIGHTThe PCW cooling water system has entered on-site installation and commissioning. The system comprises a plate heat exchanger, circulation pumps, a control panel and temperature, pressure and flow instruments. Equipment positioning, piping, panel wiring and instrument calibration are complete, with pump start/stop, temperature control and alarm interlock testing underway.
Commissioning scope
- Plate heat exchanger and circulation pump piping and pressure testing
- Control panel wiring and local/remote control transfer
- Temperature, pressure and flow signal calibration
- Pump start/stop, interlock and alarm tests

Once commissioned, the system will supply cooling water stably to process requirements; final parameters and control scope are defined by the project technical documents.