Baiyun Airport T3: negative pressure and roof cooling systems installation and commissioning
The Baiyun Airport T3 terminal project has entered installation and commissioning of the negative pressure system and roof cooling system, with pump sets, control panels and piping progressing on schedule.
ZHUOCHUANG / INSIGHTFor the Baiyun Airport T3 terminal MEP package, the negative pressure system and roof cooling system have entered installation and commissioning. Stainless-steel tanks and vertical pump sets have been positioned, pipe flanges connected, control panels wired and instruments calibrated, with standalone and integrated testing carried out by system zone.
Scope
- Negative pressure pump sets, tanks and piping
- Roof cooling system panel wiring and equipment commissioning
- Pressure, level and operating status signal integration
- Standalone trial runs and integrated system testing


The team will complete remaining commissioning and acceptance work according to the project schedule; the final scope is defined by the project technical documents.