Shenzhen Airport distribution room: backup auto-transfer (BZT) system commissioning

The backup auto-transfer (BZT) system at the Shenzhen Airport distribution room has entered commissioning, with LV panels, bus-tie and transfer logic set and tested by zone.

项目工程团队 1 min read 15
Shenzhen Airport distribution room: backup auto-transfer (BZT) system commissioning
ZHUOCHUANG / INSIGHT

Commissioning of the backup auto-transfer (BZT) system at the Shenzhen Airport distribution room is underway. Work includes verification of LV panel and bus-tie status, setting of transfer logic parameters, simulated loss-of-supply and recovery tests, and integration of SCADA signals and alarms.

Commissioning scope

  • LV distribution panels and bus-tie status checks
  • BZT logic setting and operation tests
  • Verification of simulated supply loss, transfer and recovery
  • Integration of monitoring signals, alarms and event records
BZT commissioning at Shenzhen Airport distribution room
LV panels and BZT commissioning on site

Commissioning is carried out zone by zone to minimise impact on existing power supply; the final scope is defined by the project technical documents.

Back to news

START A PROJECT

The next system starts with a high-quality conversation.

Tell us about your process, site and objectives. Our engineering team will respond within one business day.

DIRECT CONTACT

kfj77@163.comTechnical support & FAQs

OFFICE HOURS

Mon–Fri, 09:00–18:00 (CST)